|
|
| voorstelling
project | dankbrief
werkkamp 2008 |
The
Rehabilitation of Al-Shifa’a Clinic
Previously Destroyed During
Nahr el Bared Crisis 2007
1. Project’s Background and Situation
The fighting
in Nahr el Bared camp broke out on Sunday the 20th of May 2007 in the
early morning after the Lebanese security forces raided a suspected Fattah
Al-Islam safe-house in Tripoli.
The displacement of the camp civilians began on Tuesday 22nd of May during
a temporary cessation of hostilities between the Lebanese Army and Fatah
Al-Islam militants. Thousands of individuals fled the camp seeking safer
refuge, leaving their homes and all their belongings behind. This massive
displacement of civilians continued every time a cessation of hostilities
took place.
According to UNRWA, around 31,441 persons (6,199 families) were displaced.
Of those, 26182 persons (5045 families) sought refuge in Baddawi Camp.
The majority of those IDPs were hosted by the families in Baddawi; the
remaining sought shelter in schools and other displacement centers (KGs,
warehouses, mosques, clubs) in Baddawi or its surroundings. Other IDPs
were dispersed in Tripoli, Beirut, Saida, Tyre, and Beqaa, mainly in other
Palestinian camps at the homes of relatives, whose economic condition
barely helps them support their own families. The displaced refugees suffered
from very poor living conditions, mainly those in the schools and the
displacement centers, since such locations are not adapted for living.
(Figures as of August 2007)
On September 2, 2007, the Lebanese army announced the end of the hostilities
and its complete control over NBC. Shortly after, Experts from UNRWA and
Khatib and Alami (contractor assigned by the Lebanese Government to rebuild
the camp) and a number of NGOs were allowed to enter, what is now referred
to as the New Camp, to begin the emergency return operations; entrance
to the old camp is still restricted up to this date. Demining experts
handled clearing UXOs while UNRWA began clearing the rubbles and Khatib
and Alami assessed the status of the buildings. UNRWA then established
a temporary plot (plot23) in the southern side of the camp where pre-fabricated
housing units were built. These units were poorly constructed and are
not suitable for living especially with the winter season coming in Lebanon.
About 120 families currently inhabit these units. UNRWA also rented a
number of unfinished buildings and performed some minor works on them
to render them habitable. 10 buildings were rented up to this date, yet,
the conditions of these buildings are as worse as the housing units.
2.
Current Health Situation:
The increased return of the camp inhibitions coupled with the lack of
houses and the over-crowdedness, is creating miscellaneous health problems.
Add to that the lack of resources to tackle these issues, the end result
of which would be a rather complicated health crisis. Even thought there
are a number of local and international NGO working to meet the increasing
needs of the camp occupants, the latter remains to be insufficient. The
some associations worked in the health sector, some of them are PRCS,
UNRWA, UNICEF, the National Association for Social Medical Care and Vocational
Training (NASMCVT), and Al-Shifaa through their main operational Clinics
and Health Centers, however many gaps exists that hinders the proper function
and the coordination mechanism, the gaps in coordination are limiting
the ability of health workers to be able to reach all who are in need.
3.
Al-Shifaa Historical overview
Al-Shifaa’s
work started in 1970 changing names repeatedly, the first of which was”Mostawsaf
Al-Sha’bi”, and then it was changed to “Al-Jama’ya
Al-khayriya li Al-Riaa’ya Al-Shabiya”. But as of 1995 the
name was changed to “Jama’ya Al-Shifaa Al-Tebbuyeh Al-Ejtima’ya”.
Well-known as Al-Shifaa, they work through two clinics one located in
Nahr el Bared and the other in Baddawi. At the beginning the scope of
work was primitive, where they used to offer medical services through
volunteer doctors and medication through whatever in-kind donations and
free samples we reserve from various pharmacies and donors. But, with
the economical problems, the increase in population and depilated living
condition Al-Shifaa was forced to extend the scope of its services as
indicated below. However, during the NBC crisis (Nahr el Bared Camp) Al-Shifaa
center was 1st partially destroyed but still resumed it work till the
end of June, after which it was completely demolished.
4.
Pre-NBC Crisis:
4.1 Services:
Prior to the Nahr el Bared Crisis our centers used to offer the following
services:
- Consultation
covering almost all specialties
- Referrals
for more complicated cases to neighboring hospitals for symbolic fees.
- Pre-natal,
post natal as well as neo-natal services
- Laboratory
services
- Dental
services
- Guidance
and counseling center offering health education and awareness
- Emergency
services covering first aid, and minor injuries
4.2 Staff:
The staff comprised of a group of people who are working either on paid
or voluntary bases as follows:
- Three
general practitioners
- Twenty
five specialty doctors
- Two nurses
- One technician
- One volunteer
administrator
- Several
volunteers performing miscellaneous work
5. Post-NBC Crisis:
Both centers,
in Nahr el Bared and in Badawai, were still operational even after the
fighting started:
Baddawi Camp
Clinic:
Following the
displacement from Nahr el Bared to Baddawi Camp, a significant humanitarian
crisis was created. To help alleviate the crisis and cope with the situation,
Al-Shifaa center in Baddawi took the following steps to make it more functional
as an emergency center:
- Increasing
working hours (8 a.m. until late at night)
- Extending
the staff according to the work-load, by taking up volunteer nurses,
doctors, assistances and administrators
- Approaching
relevant medical parties to accommodate the increasing demand of medications
The previous
procedures in the Baddawi clinic enabled the center to accommodate up
to 160 patients daily.
Nahr el Bared
Clinic
The center
in Nahr el Bared was in the begging of the war partially destroyed and
they continued their relief work and emergency under bombing being the
only working health clinic until the end of June 2007. After war it was
completely destroyed but by filling their responsibility with the returned
families as a 24 hours medical center they continued the operations. Since
the return of the families, Al-Shifaa offered basic emergency services
and consultations, distributed free medicines, and served as shelter for
the displaced families offering food and water with the help of IRC (International
Red Cross) and still with an average of 25 patients per day.
As mentioned
above, the equipments are very primitive, the funds and donations are
diminishing, and the venue hardly confines with the conditions needed
to run a health facility, for it lacks proper hygiene and organized mechanism
of work. The following is a brief description of the center’s current
situation:
5.1 Services:
- Emergency
(24 hours)
- Consultation
(General Practitioner)
- Dressings
& Changes
- Medicines
(Free)
- Diapers
distribution
- Milk
distribution
- Clothes
distribution
5.2 Volunteers:
No. Full
Name Position
- Dr.
Tawfiq Assad Dr. General Medicine
- Dr.
Ahmad Yasin Al-Hajj Dr. General Medicine
- Mr.
Milad Samir Salami Staff Nurse
- Mr.
Ahmad Yousef Al-Tayar Nurse
- Miss.
Eva Ghinem Nurse & Secretary
- Mr.
Emad Awdi General Director
- Mr.
Ahmad Ibrahim Suleiman Cleaner
5.3 Equipments:
A lack on equipments
and medical instruments is found in Al-Shifaa Center in Nahr el Bared.
6.
Special Considerations:
It’s noteworthy
to mention that even though there are many local and international organizations
currently working in Naher Al-Bared, but none of which offer a 24-hours
emergency services (except for PRCS & Al-Shifaa). And as mentioned
previously all the workers in the center are volunteers, which demonstrate
their strong community ties and the enormous support that they are receiving.
In the recently
Plan of Nahr el Bared Rebuilding, February 2, 2008, it is proposed to
rebuild the Al-Shifaa Medical Center Hospital as it can before. The estimated
and approved dates are to begin in April 2008 to be finished October 2010.
|
| Werkkamp
2008
|
| |
| Werkkamp
2007
|
| |
|
Werkkamp
2006 |
| 
|
|